1、ErectionProgramForthe443-3P1preheatertowerNameofthedocument:TheErectionprogramofthe443-3P1preheatertowerNo.ofthedocument:GU3-方案-M-010Editingdepartment:TheEngineeringdepartmentofCBMIEditedby:LiuLiDaDate:2013-11-20Verifiedby:Date:Approvedby:Date:Version043/43目录contents一.工程概述Summary--

2、----------------------------------3二.方案编制依据Compilationbasis---------------------3三.吊装机具的选择ThechoiceofLiftinginstrument-----6四.质量安全保证体系流程图Theflowchartofqualitysafetyguaranteesystem-----11五.施工工艺过程Theconstructionprocess----------------12六.安全及文明施工Safeandcivilizedconstruction--------164

3、3/43一.工程概述Summary:HOLCIM(ECUADOR)GU3水泥厂是一条日产4500吨的水泥熟料生产线。窑尾预热器塔架是整个熟料生产线的关键部位,因其系统复杂,安装高度高,构件数量多,单件重量重而成为安装难度最大的一个子项之一。预热器塔架采用钢结构和预热器相结合的安装方式,其中钢结构的的作用是支撑整个预热器系统,提供生产操作,检修操作的平台。整个钢结构主体系统共7层,高96.4m(15m-111.4m),构件共9根H型钢,,各层平面有连接梁,上铺花纹钢板,钢结构总重约2500吨。预热器在熟料生产中主要起生料预热和物料分解的作用,整个系统分别由五级

4、旋风筒、分解炉、三次风管、喂料室等组成,设备安装分别从喂料室开始至C1旋风筒结束。预热器系统还配备有提升机、喂料机、风机、收尘器,电梯等辅助设备。HOLCIM(ECUADOR)GU3Cementisa4500t/dclinkercementproductionline.Preheatertoweristhekeycomponentofclinkerproductionline,becauseofitscomplexity,theinstallationheightishigh,thenumberofmulti-component,one-pieceheavy

5、weightandbecomedifficulttoinstalloneofthelargestonechild.Preheatertowerusingacombinationofsteelandinstallation,whichistheroleofsteelstructurestosupporttheentirepreheatersystem,providing43/43productionoperations,maintenanceoperationsplatform.Entiresteelbodysystemof7storey,96.4m(15m-

6、111.4m),memberof9H-beam,thebeamisconnectedplanarlayers,uppertreadplate,steelstructureweighingabout2,500tons.Preheaterintheclinkerproductionmainlyfromthedecompositionofrawmaterialpreheatingandtheroleoftheentiresystemrespectively,byfivecyclone,calciner,tertiaryairduct,feedroomandothe

7、rcomponents,equipmentinstallationseparatelyfromthefeedchamberbegins-C1cycloneends.Preheatersystemisalsoequippedwithbucketelevator,feeder,fan,dustcollector,elevatorsandotherauxiliaryequipments.二.编制依据Compilationbasis1.HOLCIM(ECUADOR)GU3水泥厂烧成窑尾工艺布置图。HOLCIM(ECUADOR)GU3PROJECTPREHEATERT

8、OWERGENERALARRANGEMENTDRAW

当前文档最多预览五页,下载文档查看全文

此文档下载收益归作者所有

当前文档最多预览五页,下载文档查看全文
温馨提示:
1. 部分包含数学公式或PPT动画的文件,查看预览时可能会显示错乱或异常,文件下载后无此问题,请放心下载。
2. 本文档由用户上传,版权归属用户,天天文库负责整理代发布。如果您对本文档版权有争议请及时联系客服。
3. 下载前请仔细阅读文档内容,确认文档内容符合您的需求后进行下载,若出现内容与标题不符可向本站投诉处理。
4. 下载文档时可能由于网络波动等原因无法下载或下载错误,付费完成后未能成功下载的用户请联系客服处理。