《24米以下脚手架方案》由会员上传分享,免费在线阅读,更多相关内容在行业资料-天天文库。
1、保利中辰大厦落地外脚手架方案目录一、编制依据·················································································1二、工程概况·························································································1三、材料要求······························································
2、···················3四、脚手架形式·············································································3五、施工准备·················································································4六、地下室外脚手架搭设的方案·················································5七、外脚手架的基本构造
3、·····························································5广州富利建筑安装有限公司20保利中辰大厦落地外脚手架方案八、外脚手架的搭设及拆除施工工序·········································8九、安全管理·················································································9十、落地外脚手架计算······················
4、··········································12一、编制依据1、主要依据本工程高大模板支撑专项方案依据国家现行规范标准,我公司企业标准和成功的管理经验,及工程施工图和工程招标文件编制而成。广州富利建筑安装有限公司20保利中辰大厦落地外脚手架方案工程项目施工图:广东省建筑设计研究院建筑、结构平面图,施工立面和剖面图等相关施工图。2、规范规程本脚手架安全专项施工方案主要参考以下规范和标准:《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2001);《钢结构设计规范》(GB50017-20
5、03);《建筑结构荷载规范》(GB50009-2001);《混凝土结构设计规范》(GB50010-2002);《建筑地基基础设计规范》(GB50007-2002);《建筑施工安全检查标准》(JGJ59-99);二、工程概况1、工程概述工程地点:佛山市顺德区大良镇工程名称:保利中辰大厦结构类型:框剪结构。工期要求:1279日历天;质量标准:合格建设单位:广州富利建筑安装工程有限公司监理单位:佛山禅建监理有限公司设计单位:广东省建筑设计研究院勘察单位:建材广州地质工程勘察院施工单位:广州富利建筑安装工程有限公司建设规模:总建筑面积约1
6、81445平方米广州富利建筑安装有限公司20保利中辰大厦落地外脚手架方案2、结构概况一、本工程项目共3栋高层及附属裙房,其中办公楼1座,共24层,楼高99.5米,公寓1座,共32层,楼高99米,酒店及酒店式公寓1座,共33层,楼高150米,酒店配套裙房,共5层,楼高33米,总建筑面积181445平方米,其中地下室建筑面积为55680平方米,地上建筑面积为125765平方米。地下三层,三层高度共14.4米。三、材料要求1、钢管:采用48外径,壁厚为3.0mm焊接钢管,材质符合Q235-A级钢规定。2、扣件:采用锻铸铁扣件,其材质应符
7、合现行国家标准《钢管脚手架扣件》(GB15831)规定,不得有脆裂、变形、滑丝现象,扣件表面应进行防锈处理,扣件活动部位应能灵活转动。当扣件夹紧钢管时,开口处的最小距离不大于5mm。3、安全立网应使用已经佛山市安监站认可的合格产品,要有出厂合格证和准用证,不得使用腐烂、变质和破损严重的安全立网。4、脚手板:采用钢笆片。5、挡脚板:采用18mm厚胶合板。四、脚手架形式本工程地下室地下三层(高度14.4米)脚手架采用双排单立杆扣件式钢管脚手架。五、施工准备1、技术准备广州富利建筑安装有限公司20保利中辰大厦落地外脚手架方案在施工前进行
8、图纸会审及完善施工组织设计方案这两项工作,并组织施工人员认真学习施工图纸、会审记录、施工方案和施工规范等技术文件,做好三级安全技术交底工作,减少和避免施工误差。2、物资准备一、材料准备:确保材料质量合格,货源充足,按材料进场计划分期分批进场,并规定