1、中国南方电网有限责任公司电网建设施工作业指导书第1部分:输电线路176第1部分:输电线路高压电缆安装作业指导书编码:SDXL-ZW-13SDXL-ZW-13高压电缆安装作业指导书目次1工程概况及适用范围··································································································································1412编写依据·················································
2、·····································································································1413作业流程······················································································································································1414安全风险辨析与预控················
3、··················································································································1425作业准备······················································································································································1426作业方法········
4、··············································································································································1437质量控制措施及检验标准··························································································································146179SDX
5、L-ZW-13高压电缆安装作业指导书1工程概况及适用范围1.1适用范围本作业指导书适用于110~500kV电压等级交联电缆预制式中间接头、终端头安装。1.2工程简述包括:工程的总体情况,铁塔设计型号,工程量,地形等。2编写依据表2-1编写依据序号引用资料名称1GB50168—2006《电气装置安装工程电缆线路施工及验收规范》2DL/T5161.1~5161.17—2002《电气装置安装工程质量检验及评定规程第5部分电缆线路施工质量检验》3DL409—1991《电业安全工作规程(电力线路部分)》4Q/CSG10002—2004《架空线路及电缆安健环设施标准》5Q/CSG1
6、0010—2004《输变电设备状态评价标准》6Q/CSG11105.2—2008《南方电网工程施工工艺控制规范》7CSG/MS0912—2007《电网建设工程安全和环境管理设施规范应用手册》8施工图纸9电力电缆施工手册(2002.5)10附件厂家安装说明书及技术资料179SDXL-ZW-13高压电缆安装作业指导书3作业流程图3-1作业(工序)流程图179SDXL-ZW-13高压电缆安装作业指导书4安全风险辨析与预控4.1高压电缆安装作业前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任
7、务的风险分析表。4.2按《指南》中与高压电缆安装作业相关联的《电网建设安全施工作业票》(编码:SDXL-ZW-13-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施工负责人签发。4.3施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员负责将安全措施落实到各作业任务和步骤中。4.4安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须重新办理作业票,在工作完成后上交项目部保存备查。表4-1作业任务安全基准风险指南序号